I-15 Construction Update – Thursday, August 3, 2017

Daytime Lane Closures: Lane closures will take place on Bedford Canyon Road in Corona from Foothill Parkway to Georgetown Drive from 7 a.m. to 5 p.m., Monday, August 7, through Wednesday, August 9. Trafffic flaggers will be present to direct motorists through the work zone.


Santa Ana River Work: Construction crews will begin operations below I-15 at the Santa Ana River, including grading and preparation for upcoming geotechnical exploration. Prior to this work, 50 pre-cast bat panels, pictured below, were installed last winter to provide temporary roosting for bats in this area. The bats provide protection by eating mosquitoes that can carry fatal diseases.

Ongoing Construction Work: Surveying and underground utility location work will continue throughout the project limits on shoulders, under bridges and around on- and off-ramps. This work is required to verify locations of existing underground utilities and physical properties which could affect elements of the project design.

 